Ship Shape
- Published: 03 June 2008 17:36
- Author: Margo Cole
- More by this Author
- Last Updated: 05 June 2008 13:56
- Reader Responses
A major clean-up is under way on the north shore of the River Tyne to turn an abandoned and polluted dockyard into a large-scale housing development, as Margo Cole discovered.
Shipbuilding and repair provided employment for thousands of people on the River Tyne. Now all that remains of this once thriving industry is a fascinating legacy for industrial archaeologists and hundreds of acres of prime waterfront land.
One such site is at North Shields which has been home to dry docks since the 18th century. The 13ha site was bought by the Smith's Dock Company in 1891 and rapidly became the largest ship repair yard in the world. It thrived until the middle of the 20th century, with new docks added during the 1920s and 1930s, the last – the largest dock on the Tyne – being built as late as 1953.
By the 1980s, however, the entire industry was in decline, and Smith's Dock was no exception. The yard closed in the early 1990s, and has been derelict ever since.

REUSING DOCK GATES - Three massive decommissioned dock gates have been lifted out of the water and repaired
"From the survey it seemed like a reasonable assumption that the gates could be lifted"
Ian Whitfield, Fairhurst

Shuttering - The resurrected dock gates hold back the River Tyne and are acting as shuttering for the new concrete walls
In fact, civils contractor Volker Stevin managed to lift the 230t-plus gates for Docks 4, 7 and 8. They have been repaired and are being used as shuttering to enable the contractor to build permanent concrete stop ends to the docks. A cofferdam will still be needed to build the wall at the end of Dock 6, while the remaining, smaller, docks will be sealed during piling for the new quay wall.
One of the biggest challenges is dealing with contaminated material on the site. Most of the docks have a layer of silt in them measuring anything from 0.5m to 1m in depth, and the Environment Agency is very keen that this silt does not get into the River Tyne. "The silts contain a lot of tributyltins, which were a constituent of anti-fouling paints," explains Whitfield.

NEW QUAY WALL - A series of tubular steel piles is being driven along the river bank to create a new quay wall
The 10,000m3 of silt in each of Docks 4 and 6 will have to be removed. "We will have to stabilise the silts insitu to give them some geotechnical properties so that they can be utilised elsewhere on the site," says Whitfield.
There are other contamination issues to be dealt with too. Dock 5 – which is to be refurbished and retained – had been compartmentalised into individual storage tanks. These will have to be removed very carefully and taken off site.
Other contaminants are largely confined to the location of old workshops. "We can use old Ordnance Survey maps to tell us what activities happened at what location on the site, so we know what contaminants we expect to find," says Whitfield. "But in other areas there is general demolition material from where the site was levelled and we expect to find additional contaminated material, including asbestos."
Balancing the cut and fill on site is a major challenge. As well as the vast quantities of material required to fill the docks, material is needed to raise the level of the river frontage by 1m to make sure the development is safe from future flooding.
Volker Stevin started work on the Smith's Dock site in August 2007, and is set to complete the civils programme – including new piled quay wall, site clean-up, roads and drainage – in 2009. The entire development of 1,220 homes will be completed in 2012.

Holding back the Tyne: The river frontage must be raised by 1m to protect the 1,220 new homes
The developer of Smith's Dock is Making Places, a joint venture between Cofton and Places for People.
The two firms have joined forces to buy and develop land for large scale and complex developments across the UK, allocating a £350M rolling fund for investment.
Cofton's role is to identify and purchase land, negotiate the planning process and provide the essential infrastructure. Places for People funds and builds the homes. It is known for its developments in the affordable and social housing sectors.
Smith's Dock is the JV's first project. It consists of 1,010 riverside apartments and 210 townhouses, of which all but 30 are for outright sale - a reflection of a desire to raise levels of home ownership in the area.
Project info
Project Smith's Dock, North Shields
Client Making Places
Civils contractor Volker Stevin
Contract value £15M
Contract period mid 2007-2009
Development completion 2012

