Key Crossrail shaft completed ahead of schedule

Resequencing of work by Crossrail western tunnels contractor BAM, Ferrovial, Kier (BFK) and subcontractor Barhale has enabled a key shaft to be completed nine months ahead of schedule.

The 15m diameter Fisher Street shaft in Holbourn will be used as an emegency access shaft once the new rail line is completed but the early construction means that it can be used to support BFK’s tunnelling work on a crossover tunnel below Red Lion Square.

The Fisher Street shaft was originally scheduled to be completed in August 2014 but resequencing of work enabled early completion of permanent waterproofing and concrete lining of the shaft.

Have your say

You must sign in to make a comment.

Related Jobs

Sign in to see the latest jobs relevant to you!

NCE newsletters

Linked In

Follow NCE on LinkedIn

Stay in touch through NCE's online community

crossrail_isle_of_dogs

London's £14.5bn Crossrail scheme

Full details

Find out more

Linked In

Follow NCE on LinkedIn

Stay in touch through NCE's online community